Concrete Calculator with Cement Bags and Rebar Weight

Work out the concrete volume for slabs, footings, columns, beams and stairs, the cement, sand, gravel and water for your mix, and the weight of reinforcing steel with a 12 m bar cut list. Modelling the structure in Revit? Browse our Revit families.

Slabs, footings, columns, beams, stairsCement bags, sand, gravel, waterCommon site mixes and 1:2:4 ratiosRebar weight d²/162 and exact12 m bar cut list

Calculator

Elements

Dimensions in

For beams, enter the depth below the slab so the slab volume is not counted twice. The stair flight is approximate: steps plus an inclined waist slab; add landings as slabs.

Mix and waste

Quantities per m³ of finished concrete. The first three are cement-content mixes with 0.4 m³ sand and 0.8 m³ gravel per m³, common for site-mixed concrete; your structural engineer's specification and the local code take precedence.

%

Added to the net volume. 5 % is a common allowance.

Litres of water per kg of cement.

Ready-mix truck size
Loose bulk densities for tonnes
kg/m³
kg/m³

Typical values; ask your supplier for the real figure. Used only to convert m³ to tonnes.

Prices (optional)

Type today's prices from your supplier to get a cost estimate. Leave a field empty to skip it.

Concrete volume

 

Enter your elements to see the result.

Estimate only. Quantities are for ordering and budgeting, not for design. Mix proportions, cover, laps and bar schedules must come from your structural engineer's drawings and the code that applies to your project, such as ACI 318 or Eurocode 2. Allow extra for spacers, chairs, tie wire and site losses.

Need a structural Revit model or quantity takeoff? We model it and schedule the quantities for you.

Request a project
How it works

Estimate concrete and steel in three steps

1

Add your elements

Pick slab, footing, column, beam, strip footing, stair flight or a custom volume, type the dimensions in metres or feet and how many there are.

2

Choose the mix

Use a cement-content site mix (250, 300 or 350 kg cement with 0.4 m³ sand and 0.8 m³ gravel), a nominal ratio such as 1:2:4, or your own quantities, and set the waste allowance and truck size.

3

Add the rebar

Switch to Rebar weight and list your bars, or describe a slab or footing mesh by spacing and cover. You get kilograms, tonnes, the 12 m bars to buy and a cost if you type prices.

The formulas

How much cement, sand and gravel per cubic metre

Concrete to order = net volume × (1 + waste %)
Cement bags = volume × cement (kg/m³) ÷ 50
Rebar weight (kg/m) = d² ÷ 162 ≈ 7850 × π × d² ÷ 4 ÷ 10⁶

Site mixes are often written as kilograms of cement per cubic metre with 0.4 m³ of sand and 0.8 m³ of gravel (زلط or crushed stone). For a nominal volume mix such as 1:2:4, multiply the wet volume by 1.54 to get the dry volume of materials, split it by the ratio parts, and convert cement at 1,440 kg/m³.

Worked example: a 5 × 4 m slab, 0.15 m thick, is 3 m³. At 350 kg/m³ that needs 1,050 kg of cement, which is 21 bags of 50 kg, plus 1.2 m³ of sand, 2.4 m³ of gravel and 525 litres of water at a water/cement ratio of 0.5.

Mix (per m³)Cement50 kg bagsSandGravel
Plain concrete250 kg50.40 m³0.80 m³
Foundations300 kg60.40 m³0.80 m³
Reinforced concrete350 kg70.40 m³0.80 m³
1:3:6222 kg4.40.46 m³0.92 m³
1:2:4317 kg6.30.44 m³0.88 m³
1:1.5:3403 kg8.10.42 m³0.84 m³

The first three rows are common site practice, not values quoted from a code. Codes set minimum cement contents by exposure condition, so always follow your structural specification.

Quick reference

Rebar weight per metre and per 12 m bar

Barkg/m (exact)kg/m (d²/162)kg per 12 m bar12 m bars per tonne
Ø60.2220.2222.66375
Ø80.3950.3954.74211
Ø100.6170.6177.40135
Ø120.8880.88910.6593
Ø141.2081.21014.5068
Ø161.5781.58018.9452
Ø181.9982.00023.9741
Ø202.4662.46929.5933
Ø222.9842.98835.8127
Ø253.8533.85846.2421
Ø284.8344.84058.0017
Ø326.3136.32175.7613

The exact value uses a steel density of 7,850 kg/m³. The d²/162 rule is about 0.1 % heavier and is accurate enough for site estimates. Bars per tonne are rounded down.

Add laps where bars are longer than 12 m (often 40 to 50 bar diameters; take the value from your drawings) and allow extra for chairs, spacers and tie wire.

FAQ

Concrete and rebar questions

It depends on the mix. A typical reinforced site mix of 350 kg/m³ needs 7 bags of 50 kg, plain concrete at 250 kg/m³ needs 5 bags, and a nominal 1:2:4 mix needs about 6.3 bags (317 kg). Round up to whole bags and add a waste allowance, usually around 5 %.

Multiply length × width × thickness, all in metres, to get cubic metres. A 5 × 4 m slab that is 15 cm thick is 5 × 4 × 0.15 = 3 m³. Add about 5 % for waste and spillage before you order ready-mix.

The numbers are parts of cement, sand and coarse aggregate by volume. Because dry materials shrink when mixed with water, you need about 1.54 m³ of dry material per 1 m³ of concrete. For 1:2:4 that gives 0.22 m³ of cement (317 kg), 0.44 m³ of sand and 0.88 m³ of gravel; for 1:1.5:3 it gives 403 kg of cement, 0.42 m³ of sand and 0.84 m³ of gravel.

Weight in kg per metre is the bar diameter in millimetres squared divided by 162. A Ø12 bar weighs 144 ÷ 162 ≈ 0.888 kg/m, so a 12 m bar weighs about 10.7 kg. Multiply by the total length of each diameter, including laps, to get the total weight.

Divide 1,000 kg by the weight of one bar. For Ø12 that is 1,000 ÷ 10.65 ≈ 93 bars, for Ø16 about 52 bars and for Ø10 about 135 bars. The calculator also packs your actual cut lengths into 12 m bars so you can see the offcuts.

List every element: footings, strip footings, columns, beams (depth below the slab only), slabs and stairs. Work out each volume and multiply by the number of identical elements, then add the waste allowance. Enter them as rows in the calculator to get the total in m³, the materials and the number of ready-mix trucks.